§ 9-12-37. Payment of fees.  


Latest version.
  • A.

    Any person acquiring a permit shall be subject to the following payment of permit fees and the following procedure shall be used in payment thereof:

    1.

    Initial filing fees for construction permits must be submitted with the initial permit applications.

    2.

    Additional fees related to construction permits including those related to public notice are due within 30 days of receipt of billing by the department.

    3.

    Fees related to stack testing are due within 30 days of receipt of billing by the department.

    4.

    Inspection/operating fees are assessed annually on the anniversary date of the issuance of the permit where applicable.

    a.

    Fees for asbestos removal must be submitted with the written notice of intent to remove.

    b.

    Fees for air curtain destructors must be submitted within ten days of receipt of permit.

    5.

    Fees related to modification of a permit shall be submitted with the permit application.

    6.

    Fees related to public notice necessary for the regulation of a source shall be due within 30 days of receipt of billing by the department.

    B.

    If the emissions fees assessed to a stationary air pollution source are less than $5,000.00, the fees owed shall be submitted by September 30 of the year following the year the emissions occurred. If more than $5,000.00 is owed, then the amount due shall be submitted by January 31 of the year two years after the emissions occurred.

(Code 1985, § 16-96; Ord. No. 4105, § 1, 5-26-1992; Ord. No. 4636, §§ 2, 3, 12-15-1998; Ord. No. 4867, § 1, 6-19-2001; Ord. No. 4899, § 1, 10-2-2001; Ord. No. 4981, §§ 7—9, 12-17-2002)